Senior Reporter
elizabeth.gonza[email protected]
The Office of Procurement Regulation (OPR) has found problems in how the Housing Development Corporation (HDC) selected and checked companies for its cancelled $3.4 billion housing project.
The findings are the latest in a series of OPR interventions involving HDC procurement, including complaints and challenges over other major housing projects.
The one-page statement was published on the OPR website on July 29, six weeks after HDC cancelled the process.
It said: “In carrying out its inquiry, the Office reviewed and assessed the Record of Procurement Proceedings, supporting documentation, explanations and clarifications provided by the HDC, relevant data from the Procurement Depository and other verifiable records available in the public domain.”
OPR continued: “This assessment detected issues in the interpretation and application of the legislative framework, as well as procedural gaps which gave rise to deficiencies in compliance relative to the public procurement framework.”
It said: “In particular, the Report identified shortcomings in the process used for supplier identification and in the rigour of the due diligence conducted during the pre-qualification and evaluation phases of the procurement process.”
In simple terms, OPR found problems in how HDC selected companies and checked whether they qualified for the work.
OPR did not release the full report. It directed HDC to consider the findings and take “corrective, remedial or compliance-related action” before any future contract process.
It also said: “The complaints received in relation to the procurement proceedings are being addressed by the Office separately.”
OPR added: “The Office notes that the HDC has cancelled the captioned procurement activity by Notice of Cancellation dated June 17, 2026, and affirms that the cancellation is in the public interest.”
The statement did not allege corruption, name anyone responsible or say a crime was committed. A breach of a procurement rule is not automatically a crime.
Related complaints
The OPR's findings on the $3.4 billion process sit within a wider record of complaints and procurement challenges involving HDC, some of which remain unresolved.
HDC began the Design-Build-Finance programme in 2025. Contractors were expected to design, build and finance about 3,700 homes. By December, HDC had listed Portfolio 1 as limited bidding in its procurement plan.
Former Housing Minister Camile Robinson-Regis said HDC first chose 28 contractors. By early 2026, HDC had cut that group to 18 for site visits and bids, then selected 11 intended contractors.
On April 8, HDC announced proposed awards totalling $3,481,200,221.41. The largest, $1.025 billion, was intended for Mootilal Ramhit & Sons Contracting Ltd. These were proposed awards, not signed contracts. A ten-working-day period for objections ran from April 9 to April 22.
HDC’s 11 intended awards
Contractor Proposed award
Mootilal Ramhit & Sons Contracting Ltd $1.025 billion
California Stucco Company Ltd $445.8 million
Hakim Hosein Construction Company Ltd $410.3 million
Trinidad Pro Construction Ltd $289.6 million
Keith’s Transport and General Contracting Service $232.4 million
Bristol Construction Company Ltd $229.4 million
Adam’s Project Management & Construction Ltd $200.8 million
Norris Transport Enterprises Company Ltd $192.5 million
CE Management and Services Ltd $183.8 million
Oilfield and Industrial Hardware Ltd $159.9 million
Rampersad’s General Contractors and Equipment Rental Company Ltd $111.9 million
On April 9, the Joint Consultative Council wrote to OPR after checking a private citizen's information. JCC president Fazir Khan called the issue “not minor; this is major.”
On April 13, Robinson-Regis questioned the cut from 28 companies to 18, the excluded contractors and the final 11.
On April 14, OPR ordered HDC to hold on the award of contracts. Minister in the Ministry of Housing Phillip Alexander defended the process the next day. Former prime minister Stuart Young alleged “cartel-type” behaviour and called for a criminal investigation.
NH International filed 11 challenges on April 21. OPR dismissed them on April 24 because the objections concerned an earlier selection stage and were filed too late. The panel did not decide whether the allegations were true.
HDC cancelled Portfolio 1 on June 17 under Section 33. No contract had been signed. Alexander said the homes would be re-tendered and the new programme could have about 21 projects.
OPR has not disclosed the status of the separate complaints or if any were referred to the Director of Public Prosecutions or the police.
HOW THE $3.4 BILLION HDC PROCESS UNFOLDED
DATE WHAT HAPPENED
2025 HDC began the Design-Build-Finance process for about 3,700 homes.
Dec 2025 Its procurement plan listed Portfolio 1 as limited bidding.
Early 2026 Twenty-eight companies were reduced to 18 bidders; HDC later chose 11 intended contractors.
Apr 8 HDC announced intended awards totalling $3.481 billion.
Apr 9 The standstill period began and the JCC wrote to OPR.
Apr 14 OPR ordered HDC to hold the awards while it reviewed the process.
Apr 21–24 NH filed 11 challenges; OPR dismissed them as late.
Jun 17 HDC cancelled Portfolio 1 in the public interest.
Jul 29 OPR said it found supplier-selection and company-checking problems.
Source: HDC and OPR notices; OPR challenge decisions; background supplied to Guardian Media. Dates and results are also stated in the story.
HDC before the $3.4B OPR investigation
A response to a Freedom of Information request sent by Guardian Media records another complaint against HDC on August 9, 2024, for an alleged “Breach of the Act”. OPR closed it after issuing a Section 14(1)(c) direction requiring corrective action. The entry does not identify the contract, finding or HDC's response.
OPR's public register also records five HDC challenges in 2024. Four concerned a proposed $475.8 million Santa Rosa housing award to China Harbour Engineering.
The first applications by NH International and Woodgreen Construction were dismissed because company documents were missing. NH filed again. On August 16, OPR suspended the procurement after finding “serious issues to be tried”. The panel questioned the intended contractor's technical scores, planning compliance and HDC's use of a cost-per-unit measure not stated in the tender documents.
HDC cancelled its Santa Rosa project that day. The case ended without a final decision because NH had obtained the result it requested. Woodgreen withdrew its case. A Class One Systems CCTV challenge was dismissed.
HDC asked OPR for advice on another matter. Chairman Feroze Khan said it concerned $17,575,921.33 in insurance services renewed in 2023 and 2024. OPR has not announced an outcome.
78 matters under probe
The wider OPR record also shows that the HDC matter is part of a larger body of procurement complaints.
On February 9, Guardian Media's FOIA asked OPR for “a list and summary of all cases handled by OPR” and, for each one, “whether it was referred to another authority (e.g. police, DPP, Integrity Commission), and when.”
OPR supplied 78 named complaints received between July 31, 2023 and January 28, 2026. Thirty-one ended with Section 14 directions requiring the public body to correct a breach. Twenty-two were closed for insufficient evidence. Eight ended with no irregularity found, and six were outside OPR's powers.
The Mayaro/Rio Claro Regional Corporation appeared four times. One matter lacked evidence, one ended with a direction and two remained active.
The North Central Regional Health Authority also appeared four times over alleged bid rigging, breaches and other irregularities. Three cases were closed and one ended with a direction.
Penal/Debe Regional Corporation appeared four times over alleged irregularities, a breach, bid rigging, collusion, victimisation and coercion. One matter produced investigation findings, one ended with a direction, one lacked evidence and one was outside OPR's powers.
NIPDEC, WASA, PLIPDECO and the Ministry of National Security each appeared three times. Their complaints alleged breaches, bid rigging, collusion or other irregularities. Outcomes included directions, insufficient evidence, no irregularity and findings after an investigation.
Five complaints reached the stage where OPR issued results and recommendations after an investigation. They involved PTSC, NIPDEC, the Agricultural Development Bank, Penal/Debe Regional Corporation and Giza Construction.
The appendix column headed “Status, Findings, Recommendations, Referrals” did not name a report to the DPP, police or Integrity Commission. The records do not establish whether a confidential report was made; none was identified.
The 78 entries are not OPR's full complaint count. The appendix also said 37 matters were ongoing but did not say whether they overlapped the named entries.
On August 13, 2025, OPR's online figures showed 55 open and 73 closed complaints, a total of 128. It also listed 39 investigations. A complaint may become an investigation, so those figures could be considered.
Section 14 of the Public Procurement and Disposal of Public Property Act, 2015 (Act No. 1 of 2015, as amended) in Trinidad and Tobago allows the OPR to direct a public body to follow the Act. Failure to obey without a reasonable excuse is an offence carrying a $100,000 fine. Section 44 requires OPR to give its findings after an investigation and make recommendations.
Under Section 45, OPR must report a matter to the DPP when it has reasonable grounds to suspect an offence. The DPP decides whether police should investigate and whether charges should be brought.
An informed source said an allegation need not be proved before OPR begins an investigation, but it must have enough credible information. If the inquiry points to wrongdoing, the public body must be told and allowed to respond.
“Once it goes to the DPP, the DPP takes it over from there and it's out of the hands of the OPR,” the source said.
The source said he was unaware of any OPR matter reaching the DPP. He said public challenge cases have stopped contracts and forced new tenders.
“OPR has been set up for a lot more than just pure investigation,” the source said. But he said the first court case would test the enforcement system: “It will just take the first one to get it going.”
In the Tobago Regional Health Authority's $18 million ambulance matter, OPR began an inquiry in October 2025 after a complaint by then THA Minority Leader Kelvon Morris. The police inquiry began after Morris separately wrote to the acting Police Commissioner and the Anti-Corruption Investigations Bureau in June. No public record shows an OPR referral.
Eight complaints in the FOIA list had not been resolved. One against the Deposit Insurance Corporation had been awaiting external legal advice for 769 days when OPR responded on March 26. The record does not say what the complaint alleged.
OPR refused to release its compliance, monitoring and assessment reports. It said disclosure could “potentially compromise the OPR's ongoing investigations” and reveal its methods.
The HDC inquiry has ended. Its full findings remain unpublished, and OPR has not disclosed whether it considered Section 45.
Guardian Media has made several attempts since June to get a comment from OPR officials via email, calls to its chairman and Procurement Regulator Beverly Khan and WhatsApp messages. All attempts have been futile on this matter.